OGE’s hydrogen pipeline projects
From the North Sea coast to the Ruhr region
- Wilhelmshaven coastal line (WKL)
- North Sea-Ruhr Link I (NRL I)
- North Sea-Ruhr Link III (NRL III)
- North Sea-Ruhr Link IV (NRL IV)
- Heek-Epe (HEp) – GET H2 project
- Dorsten-Marl (DoMa) – GET H2 project
- Dorsten-Duisburg-Hamborn (DoHa)
Wilhelmshaven coastal line (WKL)
Starting point: Wilhelmshaven-North
End point: Wilhelmshaven-Süd
Line length: approx. 11 km
Pipe diameter: DN 1000 mm
Federal state: Lower Saxony
IBN date specified by the core network: 2027
Start of construction: Q4 2026

North Sea-Ruhr Link I (NRL I)
Starting point: Wilhelmshaven gas pressure control and measuring station (Voslapper Groden)
End point: Dykhausen
Line length: approx. 21 km
Pipe diameter: DN 1400 mm
Federal state: Lower Saxony
IBN date specified by the core network: 2027
Start of construction: Q4 2026

North Sea-Ruhr Link III (NRL III)
Starting point: Bunde
End point: Wettringen
Line length: approx. 122 km
Pipe diameter: DN 1200 mm
Federal states: Lower Saxony and North Rhine-Westphalia
IBN date specified by the core network: 2027
Start of construction: Q4 2026

North Sea-Ruhr Link IV (NRL IV)
Starting point: Emden
End point: Rysum
Line length: approx. 22 km
Pipe diameter: DN 1200 mm
Federal state: Lower Saxony
IBN date specified by the core network: 2029
Start of construction: Q4 2028
Heek-Epe (HEp) – GET H2 project
Starting point: Heek
End point: Epe
Line length: approx. 11 km
Pipe diameter: DN 400 mm
Federal state: North Rhine-Westphalia
IBN date specified by the core network: 2025
Start of construction: 2025
Project partner: Nowega

Dorsten-Marl (DoMa) – GET H2 project
Starting point: Dorsten
End point: Marl
Line length: approx. 9 km
Pipe diameter: DN 300 mm
Federal state: North Rhine-Westphalia
IBN date specified by the core network: 2027
Start of construction: Q4 2026
Project partner: Nowega

Dorsten-Duisburg-Hamborn (DoHa)
Starting point: Dorsten
End point: Duisburg-Hamborn
Line length: approx. 39 km
Pipe diameter: DN 600 mm
Federal state: North Rhine-Westphalia
IBN date specified by the core network: 2027
Start of construction: Q4 2026
Project partner: Thyssengas

Do you have any questions about OGE’s hydrogen pipeline construction projects?
Your contact persons are:
Anika Leimbrink
Anika.leimbrink@oge.net
0160 5244270
Lisa Nohl
lisa.nohl@oge.net
0170 6387760